Civil construction and mechanical works in Jharsuguda
We build structures, roads, railway siding platforms and site facilities inside the Vedanta Jharsuguda complex. Seven projects delivered or under way, worth ₹5.21 crore.
About us
SK Construction is based in Banjari, Jharsuguda. We take civil and mechanical jobs for industrial clients and contractors, and we work to one line: transforming possibilities into reality.
- Safety first
- Helmets, vests and a site briefing before work starts.
- Skilled and experienced team
- Our crews work on live industrial sites.
- Quality construction
- Standard workmanship on every job, large or small.
- Committed and trusted
- Repeat work from the same clients, such as Chennai Radha Engineering Works.
What we build
Based on the work we have done so far.
Buildings
New building construction and canteen building extensions.
Tank and ETP structures
Overhead tank structures and effluent treatment plant structures.
Roads
Bitumen and thermoplastic road work.
Railway siding work
Platforms and retaining walls at railway sidings.
Parking and yard development
Heavy vehicle parking areas and yard preparation.
Wind barriers
Wind barrier works around coal yards.
Mechanical works
Offered alongside our civil construction jobs.
Project credentials
All work is at Vedanta, Jharsuguda. Order values are in ₹ lakh (100 lakh = ₹1 crore).
| Client | Work | Location | Order value (₹ lakh) | Contract duration | Status |
|---|---|---|---|---|---|
| Chennai Radha Engineering Works | 50KLD overhead tank structure and ETP structure work | Crew Mess | 46.00 | 90 days | Completed in 76 days |
| Trident Fabricators | Building construction work | Vedanta P-2 Casthouse-4 | 34.00 | 180 days | Completed in 186 days |
| AKP | Bitumen and thermoplastic work | Sarbahal to Banjari Gate, Vedanta | 156.00 | 45 days | Completed in 26 days |
| Chennai Radha Engineering Works | Crew canteen building extension work | Crew Mess | 136.00 | 90 days | Completed in 86 days |
| RKTC | Vedanta heavy vehicle parking development work | Near Banjari Gate, Vedanta Gate No. 2 | 36.00 | 180 days | In progress |
| SRC Infra Project | P-1 railway siding platform and retaining wall work | P-1 Railway Siding, Vedanta | 65.00 | 180 days | In progress |
| Utkal Innovatives | Wind barrier project work | New Coal Yard, Vedanta, near New Admin | 48.00 | 120 days | In progress |
| Total order value | 521.00 | ₹5.21 crore | |||